ADA Restroom Improvements - Proposed Project Schedule September 27, 2017 <br />Staff <br />Description / Notes <br />Sept. <br />Oct. <br />Nov. <br />Dec. <br />Jan. <br />Feb. <br />March <br />April <br />May <br />June <br />Building Permit <br />Review <br />Building Permit Review process started early May and <br />completed Sept. 22 <br />11 <br />Manufacture & <br />Delivery <br />Release Romtec to manufacture and deliver restroom building <br />8-10 weeks, 9/29 - 12/8 <br />Two Weeks Time Contingency - review(s), misc. coordination, <br />weather delays, 12/8 - 12/22 <br />Construction / <br />lnstllation <br />Site Work, Prep for Bldg. - foundation, concrete and flatwork, <br />concrete curing. two weeks, 12/8 - 12/22 <br />Install Building, connect utils, paint, stain etc. six weeks <br />12/22 - 2/2/18 <br />I j <br />• <br />Two Weeks Time Contingency - misc. coordination, <br />weather delays, two week 2/2 - 2/16I <br />I <br />Project Complete 2/16 <br />I <br />I <br />l <br />I <br />Bidding and <br />Contracting <br />Bidding, six weeks, 9/29 -11/22, adjusted two days for <br />Thanksgiving Holiday <br />Prepare Construction Agreement two weeks 11/27 - 12/8 <br />Notes <br />Coordinate delivery date with the contractor to make sure a <br />crane or front end loader is available to unload materials <br />Order owner supplied items beginning of October <br />Proposed schedule contains an additional four weeks for <br />review(s), coordination, weather delays and misc. <br />4 <br />