Laserfiche WebLink
City Council <br />Meeting Minutes <br />May 5, 2015 <br />Page 11 of 33 <br />the City, but constructed by the railroad. The initial budgeting two years ago estimated <br />a total project cost of $2.7 Million Dollars, with the bridge structure costing $600,000. <br />The current agreement puts the total cost of the bridge to be $1 Million Dollars <br />($800,000 for construction and $150,000 for flagging and other construction aspects). <br />Staff will prepare a budget amendment to provide full funding for the entire project. He <br />stated there was enough money in the City's 2015 budget. Staff will present options to <br />address this issue for Council to consider in the 2016 -2020 Capital Improvements <br />Program. <br />COUNCIL COMNMENTS <br />Council member Stolzmann asked what this means in terms of timeframe for executing <br />items later on this year City Manager explained the City has an agreement, which <br />requires more work from the railroad. It does not commit the railroad to any specific <br />timeframe for the construction. The City, along with other communities is trying to <br />determine when construction may happen. There is some chance the construction may <br />begin this year, but there are no assurances. <br />Council member Stolzmann inquired about the easement from the center of the track, in <br />response to an email from Erik Hartronft and Randy Caranci. The question was how far <br />out from the middle of the track would the fence be placed. She asked if the City has to <br />fence south of Pine Street if the easement is only 25' instead of 18'. <br />City Manager Fleming reported meeting with Erik Hartronft and Randy Caranci this <br />aftemoon to address the issue of fencing along the project. Everyone agreed on <br />minimizing the amount of land fenced off from parking. BNSF has agreed from Griffith <br />to Pine Street would be 18' from the center of the rails to the fence. They have <br />proposed the fence be located 25' from the centerline south of Pine Street. Everyone <br />involved has tried to get the railroad to agree to an 18' or smaller right -of -way fence <br />location. Staff intends to continue to work with the railroad to scale the fencing back to <br />18' south of Pine Street. He explained it is very difficult to negotiate with the railroad <br />and it takes months to get a response. He urged Council to consider the agreement <br />and allow what can get in place. <br />Council member Stolzmann asked if the agreement required a fence south of Pine <br />Street. Planning and Building Safety Director Russ explained the agreement does not <br />require the fence. The original cost of the bridge was reduced by $1 Million Dollars <br />when the City agreed to a fence between Griffith and Pine. There was a shed to protect <br />pedestrians from flying ballast and there was a different bridge structure. When the <br />fence was proposed, the cost was lowered. Subsequently, with desire to get downtown <br />parking, staff tried to get the fencing south of Pine Street. Because of the steepness of <br />slope south of Pine Street, the railroad requires a standard 25' vehicle access to <br />maintain the track. The railroad has three divisions: Real Estate, Engineering and <br />Operations and all three must approve the right -of -way. <br />