City of Louisville - Department of Public Works Engineering Division <br />Underpass Conceptual Designs - Engineers Opinion of Probable Cost Ki coley)» Horn <br />South Street & CO-42 - Underpass Date: 6/17/2021 <br />KH Project Number: 096489003 Prepared By: KK <br />Project Number: Checked By: MEC <br />DETAILED CONSTRUCTION BID ITEMS <br />ITEM NUMBER <br />ITEM DESCRIPTION <br />UNIT <br />COST <br />QUANTITY <br />AMOUNT <br />202-00010 <br />Clearing and Grubbing <br />LS <br />$ 15,000 <br />1 <br />$ 15,000 <br />202-00010 <br />Removal of Tree <br />EA <br />$ 700 <br />2 <br />$ 1,400 <br />202-00019 <br />Removal of Inlet <br />EA <br />$ 1,700 <br />3 <br />$ 5,100 <br />202-00021 <br />Removal of Manhole <br />EA <br />$ 900 <br />2 <br />$ 1,800 <br />202-00035 <br />Removal of Pipe <br />LF <br />$ 35 <br />925 <br />$ 32,375 <br />210-00050 <br />Reset Fire Hydrant <br />EA <br />$ 7,000 <br />2 <br />$ 14,000 <br />202-00200 <br />Removal of Sidewalk <br />SY <br />$ 30 <br />280 <br />$ 8,400 <br />202-00220 <br />Removal of Asphalt Mat <br />SY <br />$ 9 <br />1,480 <br />$ 13,320 <br />202-00202 <br />Removal of Gutter <br />LF <br />$ 16 <br />300 <br />$ 4,800 <br />202-00203 <br />Removal of Curb and Gutter <br />LF <br />$ 13 <br />700 <br />$ 9,100 <br />202-00206 <br />Rem Conc Curb Ramp <br />SY <br />$ 30 <br />130 <br />$ 3,900 <br />202-05030 <br />Sawing Asphalt Material (10 Inch) <br />LF <br />$ 8 <br />40 <br />$ 320 <br />203-00010 <br />Unclassified Excavation (Complete In Place) <br />CY <br />$ 30 <br />2,630 <br />$ 78,900 <br />206-00000 <br />Structure Excavation <br />CY <br />$ 30 <br />13720 <br />$ 411,600 <br />206-00100 <br />Structure Backfill (Class 1) <br />CY <br />$ 42 <br />60 <br />$ 2,520 <br />304-06007 <br />Aggregate Base Course (Class 6) <br />CY <br />$ 55 <br />840 <br />$ 46,200 <br />403-00721 <br />Hot Mix Asphalt (Patching) (Asphalt) <br />SY <br />$ 72 <br />160 <br />$ 11,520 <br />504 <br />Retaining Wall <br />SF <br />$ 100 <br />6,395 <br />$ 639,450 <br />514-00048 <br />Pedestrian Railing (48 Inch) <br />LF <br />$ 180 <br />80 <br />$ 14,400 <br />603 <br />14 Foot Concrete Box Culvert (Precast) <br />LF <br />$ 3,000 <br />100 <br />$ 300,000 <br />603-83008 <br />8 Inch Sewer Pipe <br />LF <br />$ 80 <br />865 <br />$ 69,200 <br />604-31010 <br />Manhole Box Base (10 Foot) <br />EA <br />$ 15,000 <br />6 <br />$ 90,000 <br />606-00301 <br />Guardrail Type 3 (6-3 Post Spacing) <br />LF <br />$ 30 <br />60 <br />$ 1,800 <br />608-00000 <br />Concrete Sidewalk <br />SY <br />$ 70 <br />280 <br />$ 19,600 <br />608-00026 <br />Concrete Bikeway (6 Inch) <br />SY <br />$ 70 <br />770 <br />$ 53,900 <br />608-00050 <br />Brick Pavers <br />SF <br />$ 50 <br />2,970 <br />$ 148,500 <br />609-21020 <br />Curb and Gutter Type 2 (Section II-B) <br />LF <br />$ 36 <br />170 <br />$ 6,120 <br />610-00026 <br />Median Cover (6 in Pattem Conc) <br />SF <br />$ 16 <br />960 <br />$ 15,360 <br />619 <br />Proposed Underpass Drainage <br />LS <br />$ 100,000 <br />1 <br />$ 100,000 <br />619 <br />Waterline Relocation/Lowering <br />LS <br />$ 75,000 <br />1 <br />$ 75,000 <br />619 <br />Sanitary Encasement <br />LS <br />$ 3,000.00 <br />1 <br />$ 3,000 <br />622-00270 <br />Bollard <br />EA <br />$ 600 <br />3 <br />$ 1,800 <br />DETAILED CONSTRUCTION BID ITEMS (SUBTOTAL) (A) <br />$ 2,198,385 <br />GENERAL CONSTRUCTION BID ITEMS <br />ITEM NUMBER <br />ITEM DESCRIPTION <br />% RANGE <br />% USED <br />COST <br />Construction Stormwater Management (Erosion Control/SWMP) <br />3%-10% of (A) <br />5% <br />$ 110,000 <br />Drainage/Water Quality <br />3%-10% of (A) <br />3% <br />$ 66,000 <br />Hardscape/Finishes/Materials <br />1%-5%of(A) <br />5% <br />$ 110,000 <br />Landscape Plantings <br />1%-15% of (A) <br />12% <br />$ 263,900 <br />Public Art <br />1%-3%of(A) <br />1% <br />$ 22,000 <br />Signing and Striping <br />1%-5% of(A) <br />1% <br />$ 22,000 <br />Site Elements <br />1%-10%of(A) <br />2% <br />$ 44,000 <br />Site Irrigation <br />1%-5%of(A) <br />4% <br />$ 88,000 <br />Site Lighting <br />1%-10% of(A) <br />7% <br />$ 157,900 <br />Soil Prep and Amendment <br />1%-10% of (A) <br />3% <br />$ 66,000 <br />Utilities <br />3%-10%of(A) <br />6% <br />$ 132,000 <br />GENERAL CONSTRUCTION BID ITEMS (SUBTOTAL) (B) <br />$ 1,081,800 <br />CONSTRUCTION BID ITEMS (TOTAL) (C) <br />$ 3,280,185 <br />CONSTRUCTION ALLOWANCES <br />Force Account (Utilities) <br />1%-2% of (C) <br />1% <br />$ 32,900 <br />Force Account (Misc.) <br />10%-15% of (C) <br />15% <br />$ 492,100 <br />Construction Engineering, Management, Survey, and Traffic Control <br />5%-25% of (C) <br />10% <br />$ 328,100 <br />Temporary Traffic Control <br />5%-25% of (C) <br />15% <br />$ 492,100 <br />Mobilization <br />5%-10%of(C) <br />10% <br />$ 328,100 <br />CONSTRUCTION ALLOWANCES (D) <br />$ 1 673 300 <br />TOTAL CONSTRUCTION COST (E) (C + D)) $ 4,953,485 <br />DESIGN, CONTINGENCIES, AND ROW <br />Design Engineering (City, Consultant, Subconsultants) <br />5%-30% of (E) <br />30% <br />$ 1,486,100 <br />Contingencies <br />(15%-50%) of (E) <br />50% <br />$ 2,476,800 <br />ROW <br />$50/SF <br />0 <br />$ - <br />i <br />DESIGN, CONTINGENCIES, AND ROW (SUBTOTAL) (F) <br />$ 3,962,900 <br />PROJECT TOTAL (2021) (E + F)I $ 8,916,385 <br />ESCALATION (5%) <br />PROJECT TOTAL (2022) <br />$ 9,362,204 <br />PROJECT TOTAL (2023) <br />$ 9,830,314 <br />PROJECT TOTAL (2024) <br />$ 10,321,830 <br />PROJECT TOTAL (2025) <br />$ 10,837,922 <br />Assumptions <br />on the east side of CO-42 is co-owner by Boulder County, City of Louisville, and City of Lafayette and is not included in ROW. <br />no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market <br />of probable costs provided herein are based on the information known to Engineer at this time and represent only the Engineer's judgment as a design <br />with the construction industry. The Engineer cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its <br />costs. <br />Open Space located <br />The Engineer has <br />conditions. Opinions <br />professional familiar <br />opinions of probable <br />https://kimleyhorn.sharepoint.com/sites/MT_Denver_SurfaceTransportation/Shared Documents/Louisville Underpass Concepts/20210615 - Louisville Underpass Concepts - Cost Estimate.xlsx <br />