SUBJECT: SIGNAGE AND WAYFINDING
<br />DATE: NOVEMBER 10, 2020 PAGE 2 OF 2
<br />Please recall that the "Phase 1 Wayfinding Signage" project has been incorporated in
<br />the proposed 2021 Budget for a cost of $130,000. The signage for this phase was taken
<br />directly from the existing plan and includes: secondary monument signs (2), tertiary
<br />monument signs (2), directory kiosks (2), pedestrian pole mounted signs (1), and
<br />vehicular pole mounted signs (5). Staff used cost estimates from Arthouse Design done
<br />in 2017 to project the 2021 budget for an initial phase of work. The table below displays
<br />the original cost estimate by each sign type, and then staff has added the three columns
<br />at the right for the LRC's budget discussions.
<br />Sign Types
<br />Identifier
<br />Cost Estimate
<br />Utilities Cost
<br />Landscaping
<br />Total Cost
<br />Cost Escalation
<br />In URA
<br />URA Budget
<br />Primary Monument
<br />A
<br />$ 21,000
<br />$ 5,000
<br />$ 500
<br />$ 26,500
<br />$ 28,885.00
<br />Secondary Monument
<br />B
<br />$ 17,000
<br />$ 5,000
<br />$ 500
<br />$ 22,500
<br />$ 24,525.00
<br />2
<br />$ 49,050.00
<br />Tertiary Monument
<br />C
<br />$ 11,000
<br />$ 5,000
<br />$ 500
<br />$ 16,500
<br />$ 17,985.00
<br />2
<br />$ 35,970.00
<br />Illuminated Bollard
<br />D
<br />$ 5,000
<br />$ 5,000
<br />$ 5,450.00
<br />Directional Marker
<br />E
<br />$ 1,550
<br />$ 1,550
<br />$ 1,689.50
<br />Directory Kiosk
<br />F
<br />$ 9,500
<br />$ 9,500
<br />$ 10,355.00
<br />2
<br />$ 20,710.00
<br />Interpretive Sign
<br />G
<br />$ 5,000
<br />$ 5,000
<br />$ 5,450.00
<br />Ped Pole Mounted
<br />H
<br />$ 3,700
<br />$ 3,700
<br />$ 4,033.00
<br />1
<br />$ 4,033.00
<br />Vehicular Pole Mounted
<br />J
<br />$ 3,050
<br />$ 3,050
<br />$ 3,324.50
<br />5
<br />$ 16,622.50
<br />District Seal
<br />L
<br />$ 1,650
<br />$ 1,650
<br />$ 1,798.50
<br />Pole Mounted Banners
<br />M
<br />$ 2,650
<br />$ 2,650
<br />$ 2,888.50
<br />TOTAL COSTS
<br />$ 97,600
<br />$ 106,384.00
<br />$ 126,385.50
<br />Staff's next step in this area is to contact the sign company previously involved for
<br />updated project quotes. This will provide an updated project cost as well as a better
<br />sense of future sign costs. Economic vitality staff will also set meetings with Planning
<br />and Public Works to begin work on the specific site locations; the original plan only
<br />provides general areas.
<br />RECOMMENDATION:
<br />Review the City's Signage & Wayfinding Plan and provide any questions or feedback to
<br />staff.