Laserfiche WebLink
Scenarios Effective Interest Effective Interest <br />Rate (Oct 2020) Rate Q2 2021) <br />20yr Group (5yr Interest Only) — PFM 2.3% 2.4% <br />20yr City — HTS 1 2.4% 2.5%* <br />*PFM and HTS rates were the same for Oct, 2020 as they both pull from market <br />conditions. Staff have not confirmed market rates directly with Hilltop. The <br />difference in effective interest rates in associate with the CWCB loan. <br />With a minor change in bond interest rates, the greater impacts to the funding scenarios are <br />related to the escalation in construction costs for the delay and the settlement amount both <br />resulting from the lawsuit. Delay impacts have increased the finance amount $18 million with an <br />additional $15 million for the settlement that is currently not projected to be financed. Given the <br />timing, the first bond payment for 2021 is significant smaller creating a shift of funds from 2021 <br />to 2022. The below table shows the impact for each impact from the prior 2020 estimate for a <br />total projected increase to Louisville of $2.2 million through the total bond period ending 2055. <br />Louisville <br />Payments <br />2021 <br />2022 <br />2023 <br />2024 <br />2025 <br />2026 <br />2027 <br />Total All <br />Payments <br />2020 Estimate <br />$1.8M <br />$575k <br />$575k <br />$575k <br />$573k <br />$1.2M <br />$1.2M <br />$23.3M <br />Delay Increase <br />-$400k <br />$64k <br />$64k <br />$64k <br />$66k <br />$101.2k <br />$101.3k <br />$24.9M <br />Settlement Increase <br />$157.5k <br />$157.5k <br />$157.5k <br />$472.5k <br />Revised Estimate <br />$1.4M <br />$797k <br />$797k <br />$797k <br />$639k <br />$1.3M <br />$1.3M <br />$25.5M <br />The revised estimate for Windy Gap has been included in the Initial 6-yr CIP Plan. The entirety <br />of the Initial CIP Plan has been incorporated into the current utility rate model and is showing no <br />need to modify the proposed 2% annual increases for the water utility. The CIP process is still in <br />the early phases and further evaluations that are underway or planned to be conducted throughout <br />2021 will likely have additional projects needed and will require further analysis on rate impacts. <br />Alternative Response Timing <br />As mentioned in the Timeline, Northern is requesting that participants provide their final <br />financing commitment within 1 month instead of the 3 months as outlined in the allotment <br />contract. The driver for this request is related to the construction escalations. The change order <br />from Barnard (contractor) to delay the start date 3 months from May 2021 to August 2021 was <br />approximately $7.1 million and is based on a 1 month turn around on the Finance commitment. <br />If any of the participants requires the full 3 months, this change order amount would need to be <br />extended the additional two months and would have an assumed cost impact of $2 to $5 million <br />to the project. Louisville's prorate portion of this estimate would $63,000 to $158,000. Further, <br />it is possible, that the full cost impacts would be assigned to those participants that request any <br />extra time beyond the 1 month. Therefore the City's risk could increase beyond the prorate share. <br />The consensus at the May 4th Participants Meeting was to avoid additional delays and move as <br />quickly as possible. <br />13 <br />