Account <br />Project Manager <br />(POC) <br />City Department <br />Project Description <br />2)24 Quarterly CIP Update - Info Cur ent as of July 17, 2024 <br />2024 2024 <br />Budget Expenditures <br />2024 % Spent YTD <br />Annum of initial Cumulative Project <br />budget approval Progress <br />allIL Notes on Project <br />501498-640001 Ben F/Cory P PUBLIC WORKS WATER FUND Machinery & Equipment $ 38,050 - 0% 2023 0 - 25% Complete Various equipment, purchases are in process awaiting delivery and billing. <br />501498-640045 Justin F/Cory P PUBLIC WORKS WATER FUND Meters $ 1,900,000 $ - 0% 2023 In Design Preparing for 2025 meter replacement. <br />501498-640148 Justin F PUBLIC WORKS WATER FUND Chemical Mixing Equip Replace $ 13,604 $ - 0% 2022 Complete Complete. <br />501498-660141 Justin F PUBLIC WORKS WATER FUND Filter Media Replacement -No WTP $ 616,000 $ 7,738 1% 2023 0 - 25% Complete Awarded- Reviewing submittals Planned construction w Fall/Winter 2024. <br />501498-660182 Tyler T PUBLIC WORKS WATER FUND Water Line Replacement $ 926,051 $ 354 0% 2023 Complete Complete Q42023. <br />501499-620119 Justin F PUBLIC WORKS WATER FUND Utilities Electrical Assessment $ 172,316 $ 29,790 17% 2020 Close-out Closeout paperwork/final payment. Working on rebate submittal to Xxel for LED lighting <br />installation. <br />501499-620149 Cory P/Justin F PUBLIC WORKS WATER FUND SCV9TP Administration Bldg $ 2,300,000 $ 117 0% 2024 Out to Bid Currently reviewing Architect design service bids. Tentative award in August 2024. <br />501499-620150 Justin F/Cory P PUBLIC WORKS WATER FUND Harper Pump Station Improvement $ 200,000 $ 0% 2024 Delayed Harper and Lateral combined into Raw Water Integration Protect FY2028/29. <br />501499-630146 Cory P PUBLIC WORKS WATER FUND Marshall Lake Sediment Control $ 350,000 $ 0% 2020 Delayed Project is in coordination with FRICO (owner/operator of Marshall Lake). Delayed. <br />501499-650015 Paulina B/ Cory P PUBLIC WORKS WATER FUND Computer -Hardware $ 79,000 $ 23,042 29% 2023 51%- 75% Complete Still working with vendor to replace servers and equipment for SCADA infrastructure. <br />501499-660190 Cory P PUBLIC WORKS WATER FUND NCWCD-Windy Gap Firming Proj $ 512,000 $ 969,832 189% 2021 51%- 75% Complete Annual debtpayment- Project schedule for completion in 2025. <br />501499-660231 Justin F/Cory P PUBLIC WORKS WATER FUND Louisville Lateral Ditch Pipin $ 3,016,000 $ 0% 2024 Delayed Harper and Lateral combined into Raw Water Integration Project FY2028/29. <br />501499-660236 Tyler T PUBLIC WORKS WATER FUND SBR Ditch Lining $ 27,977 $ 19,457 70% 2018 Close-out Closed Out Q12024. <br />501499-660284 Cory P/Justin F PUBLIC WORKS WATER FUND Utility Master Plan (%) $ - $ 4,178 0DIV/0! 2022 76% - 100% Complete Wrapping up final report/IT dashboard integration. <br />501499-660289 Cory P PUBLIC WORKS WATER FUND Raw Water Infrastructure $ 500,000 $ 0% 2021 Out to Bid Soliciting quotes for easement acquisitions. <br />501499-660295 Justin F PUBLIC WORKS WATER FUND SCWTP Residual Management $ 5,882,738 $ 24,710 0% 2023 In Design Currently in 30% design phase. <br />501499-670000 Cory P PUBLIC WORKS WATER FUND Water Rights $ 250,000 $ - 0% 2021 Complete $2.8 million purchase closed. Returning to purchasing water rights as they become <br />available. <br />1 I <br />502498-640000 Ben F PUBLIC WORKS <br />502498-660183 Tyler T PUBLIC WORKS <br />502498-660296 Justin F PUBLIC WORKS <br />502498-660297 Tyler T PUBLIC WORKS <br />502499-640001 Cory P PUBLIC WORKS <br />502499-640149 Cory P PUBLIC WORKS <br />502499-640159 Tyler T PUBLIC WORKS <br />502499-660284 Cory P PUBLIC WORKS <br />502499-660285 Justin F PUBLIC WORKS <br />502499-660298 Paulina B PUBLIC WORKS <br />1 I <br />503499-630096 Tyler T PUBLIC WORKS <br />503499-630150 Tyler T PUBLIC WORKS <br />503499-640000 Ben F PUBLIC WORKS <br />PUBLIC WORKS <br />PUBLIC WORKS <br />503499-660273 Tyler <br />503499-660287 Tyler <br />520799-630168 <br />520799-630169 <br />520799-630173 <br />David B <br />David B <br />Bryon W <br />GOLF <br />GOLF <br />GOLF <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />WASTEWATER <br />FUND <br />STORMWATER <br />FUND <br />STORMWATER <br />FUND <br />STORMWATER <br />FUND <br />STORMWATER <br />FUND <br />STORMWATER <br />FUND <br />GOLF COURSE <br />FUND <br />GOLF COURSE <br />FUND <br />GOLF COURSE <br />FUND <br />(Fund 501 Total I $ 17,380,085 I $ 1,081,180 I 6%I <br />WWTP Vehicle & Equipment Replacements $ 516,214 $ 0% 2023 76% - 100% Complete Purchases are in process awaiting delivery and billing. <br />Sewer Utility Lines $ 151,627 $ - 0% 2017 Close-out Closed out Q12024. <br />CTC Lift Station Improvements $ 175,265 $ - 0% 2023 In Design Bypass complete. Additional improvements awarded and parts are on order. Budget <br />amendment to $500k. <br />Sewer Pipeline Rehab/Replace $ 691,582 $ 2,726 0% 2023 Complete Closed Out Q12024. <br />Machinery & Equipment $ 80,350 $ 0% 2023 51%- 75%Complete Pressure washer purchased. Fork Lift in process, waiting for delivery date. <br />Secondary Process Probes $ 50,000 $ 1,652 3% 2021 51%- 75% Complete Equipment is being installed and set for startup. <br />Sewer Service Lateral Backflow $ 130,000 $ 0% 2024 Not Started 2024 Protect Not Started. <br />Utility Master Plan (50%) $ 37,015 $ 18,490 50% 2022 76% - 100% Complete Draft report under review. <br />WWTP Solids Handling Upgrade $ 4,441,425 $ 160,890 4% 2021 0 - 25% Complete Council Construction award May 7, 2024. Majority of equipment on order. Finalizing <br />construction set, mobilize August/September. <br />Fiber Optic Loop City Rd/Redtail $ 54,210 $ 0% 2023 On hold Waiting on Red Tail development. Carryover 2024. Now that Red Tail has been approved <br />we will work to determine the timing on fiber to the larger project. <br />(Fund 502 <br />Detention Pond Maintenance <br />Drainageway Al at Garfield & C <br />Motor Vehicle/Road Equipment <br />Storm Water Quality Master Pla <br />Storm Water Quality Master Plan <br />Fund 503 Total <br />Short Game Area Upgrade <br />Putting Green Enlargement <br />Parking Lot Improvements 60% <br />15 6,327,688 I <br />$ 623,784 $ 26,103 4% 2021 26% - 50% Complete 2024 Storm Project in progress. <br />$ 962,824 $ 80,000 8% 2020 Close-out Closed Out Q2 2024. <br />2024 76% - 100% Complete Vehicle purchase agreement, waiting delivery. <br />$ 186,078 I <br />103,061 <br />150,000 $ <br />328,019 $ <br />41,250 <br />5,000 <br />50,000 <br />40,379 <br />3%I <br />0% <br />0% <br />12% <br />0% <br />0% <br />0% <br />2024 Out to Bid <br />2021 In Design <br />2023 <br />2024 <br />2024 <br />On hold <br />On hold <br />76%- 100% Complete <br />■ 1 <br />Out to bid for construction Q4 2024-Q2 2025 <br />Design work in progress to be completed Q12024 Construct Q1-Q22025 <br />Still in initial phase <br />Project on hold. <br />Parking lot resurfaced in July 2024. Billing to come via Public Works. <br />12 <br />